Good morning. This is my first post so I hope this is the appropriate forum. I am completing the tower and 8 ft aermotor. In a few weeks I have a crane on-site for a separate project. Apparently the crane operator has some experience doing this.
Anyway, I would appreciate any advice or experience related to rigging for lift. My plan is to hoist the lower legs off the ground using my JD so I don't twist the legs. The crane will rig and lift vertical. So, to avoid damaging any portion of the mechanism or tail vane, what's the best rigging?
TIA.
Erecting the tower and motor
-
- Posts: 20
- Joined: Fri Oct 02, 2020 5:22 pm
- Location: Virginia
Re: Erecting the tower and motor
Long strap just under the mast pipe base. 90 degrees from the furling mechanism.
This also takes a lot of weight off the legs of the tower. You still need to lift the bottom of the tower (two people) until the head/mill is hanging in the air by the crane.You do not have the required permissions to view the files attached to this post.
-
- Posts: 20
- Joined: Fri Oct 02, 2020 5:22 pm
- Location: Virginia
Re: Erecting the tower and motor
That is EXACTLY what I was looking for. Thanks very much.
Re: Erecting the tower and motor
Anything to do with windmills, this is the right place Steve.
Call Dan Benjamin for parts. P M me for the phone number. IF YOU TALK TO HIM, AND HE HELPS YOU, THEN BUY FROM HIM. IT CREATES GOOD KARMA.